   Air Quality Standards and Air Pollution Control Rules  

    A. After the APCP receives an odor control plan they shall perform a completeness review. Within thirty (30) days of receipt, the APCP shall notify the facility if the plan contains all the elements of a complete odor control plan. If found incomplete, the APCP shall give the facility a written explanation of the plan.s deficiencies.

  B. Within sixty (60) days after determining an odor control plan submittal is deemed complete, the APCP shall approve or disapprove the plan. During this sixty (60)- day technical review period, the APCP may request additional information needed for review.

 